NASA has laid out how it plans to get astronauts back on the Moon: an Earth-orbit test flight, Artemis III, in 2027, followed by a landing attempt on Artemis IV in 2028. The agency's update, published on 4 November 2026, builds on a briefing that NASA Administrator Jared Isaacman and other leaders gave on 23 October.
What will Artemis III actually do?
Artemis III is no longer a landing mission. According to NASA, four astronauts will fly on the Orion capsule, launched on the Space Launch System (SLS) rocket, for a planned 14-day mission in Earth orbit. The aim is to test rendezvous, docking and operations between Orion and test vehicles of the lunar landers being built by SpaceX and Blue Origin.
NASA describes the sequence like this: Blue Origin first launches a Blue Moon lander test article into Earth orbit; SLS then launches Orion and its crew, which docks with it; SpaceX then launches a Version 3 Starship lander test article, and Orion undocks from Blue Moon and docks with Starship. Independent coverage, such as Universe Today and Northeast Times, reports the same broad outline, with the test flight placed in summer 2027. Reports differ on some details of where each docking takes place, so treat the exact orbits as provisional.
| Mission | Year | What NASA says it will do |
|---|---|---|
| Artemis III | 2027 | 14-day Earth-orbit test; Orion docks with Blue Moon and Starship test vehicles |
| Artemis IV | 2028 | Crewed Moon landing attempt, with Starship and Blue Moon both targeting 2028 |
What changes for the Artemis IV landing?
For Artemis IV, astronauts launch on Orion atop SLS from Kennedy Space Center. SpaceX's Starship would refuel in Earth orbit, meet Orion and carry it towards the Moon. Blue Origin would use transfer stages to push its Blue Moon Mark 2 lander towards the Moon, where it would meet Orion in a closer lunar orbit before descending. NASA says both companies are targeting a crewed landing in 2028.
NASA is also weighing two upper-stage options for SLS: the current interim cryogenic propulsion stage and a stretched version of ULA's Centaur V that carries more propellant. For the first moonwalks, NASA and Axiom Space plan a lighter "Sortie suit" that weighs roughly half as much as the larger suit, which will still be used on longer future missions.
What should readers watch next?
Hardware for Artemis III is on track, NASA says, with processing timelines cut by about half, and the agency reports redesigning and testing a critical fuel-line component in-house in five months at roughly one-tenth of an earlier vendor estimate. Isaacman is quoted as saying: "This is a very energized NASA, and these updates are only a small part of that story."
For readers in the UK, Europe, the US and the Gulf, launches will be shown on NASA's own channels; the launch date had not been fixed beyond "2027" in the sources used here. Follow our wider science and world coverage on Pulse for updates when NASA names a date.
Frequently asked questions
Is Artemis III a Moon landing?
No. NASA describes Artemis III as a roughly 14-day Earth-orbit test of docking and operations with commercial lander test vehicles.
When is the first crewed Moon landing planned?
NASA is targeting Artemis IV in 2028, with both SpaceX and Blue Origin working towards that date.
Editorial desk
Stories signed by the Cultvia editorial desk follow our editorial policy; every story lists its sources at the end and errors are fixed under our corrections policy.
Last updated:
What changed?
- : First published
Sources
- NASA: plans to accelerate Artemis — NASA, 5 November 2026
- NASA Updates Artemis Program, Adding a Mission and Delaying Lunar Landing — Universe Today, 24 October 2026
- NASA details moon lander plans with Artemis III test flight set for summer 2027 — Northeast Times, 24 October 2026